Due to the customer’s facility operating 24 hours a day / 7 days a week, we were provided with a short timeframe to complete this switchgear retrofit.
The superintendent on the project provided the customer with a hour-by-hour schedule, as to what will be completed.
We set up (3) 12 hour shifts, and successfully completed the project, in the scheduled 36 hour timeframe.